The MTA spent nearly twice as much on consultants for the Second Avenue Subway as it did to actually dig the tunnel from 63rd to 96th streets, a damning new assessment revealed.
The 400-page report from researchers at New York University also revealed that the MTA’s failure to properly supervise the outside firms allowed costs to spiral in other key ways.
Contractors and unions overstaffed the project, dug caverns for platforms that were double the necessary size and drew up station designs so bespoke that each of the three new stops has escalators made by a different manufacturer.